NBN still 'on track' for 2020 completion

By Stephen Withers on Nov 14, 2017 12:28PM
NBN still 'on track' for 2020 completion

Editor's Picks

IoT Explained: What is the Internet of Things in Australia (June 2022)

5 essential digital transformation ideas

Top 5 Benefits of Managed IT Services

Venom BlackBook Zero 15 Phantom

NBN Co reports an additional 700,000 premises were connected in the last quarter.

NBN Co's report for the quarter ending 30 September 2017 shows another 708,000 premises were “ready for service”, bringing the total to 6.4 million.

The “ready to connect” figure was slightly lower at 6.1 million, but the company pointed out that this means more than half of the premises in Australia are now able to order an NBN plan from a retail service provider.

By the end of the quarter, 2.9 million premises had actually activated services.

The lag between premises being ready to connect and actually activated is inevitable, but activations were up 115 percent year-on-year, while the number of connections 'only' increased by 92 percent.

Newsletter Signup

Get the latest business tech news, reviews and guides delivered to your inbox.

I have read and accept the privacy policy and terms and conditions and by submitting my email address I agree to receive the Business IT newsletter and receive special offers on behalf of Business IT, nextmedia and its valued partners. We will not share your details with third parties.

As for the multi-technology mix, NBN Co reported that more than 2.8 million ready for service premises are connected using fibre to the node (FTTN) or fibre to the building (FTTB), and 1.1 million by HFC.

The remaining 2.5 million are served by fixed wireless (545,588), satellite (421,028), and fibre to the premises (FTTP; 1,559,972).

“Strong foundations have been laid by the hardworking NBN team, along with our delivery partners and retailers, playing a significant role in accelerating the rollout and activating services at an extraordinary pace,” said CEO Bill Morrow.

“With confidence we seek to take it a step further to deliver the biggest deployment year in NBN history, which will bring us to three quarters of eligible premises ready for service by the end of fiscal year 2018.”

NBN Co officials said the current progress meant the company is on track to complete the rollout by 2020.

Copyright © BIT (Business IT). All rights reserved.
Tags:
broadband nbn services telco
By Stephen Withers
Nov 14 2017
12:28PM
0 Comments

Related Articles

  • Aussie Broadband trims losses as market share grows
  • ACCC: 75 percent of NBN plans on at least 50Mbps speeds
  • NBN Co reveals new FTTN upgrade locations, reports strong first half of FY21
  • NBN Co pauses new HFC orders
Share on Twitter Share on Facebook Share on LinkedIn Share on Whatsapp Email A Friend

Most Read Articles

5 essential digital transformation ideas

5 essential digital transformation ideas

Top 5 Benefits of Managed IT Services

Top 5 Benefits of Managed IT Services

IoT Explained: What is the Internet of Things in Australia (June 2022)

IoT Explained: What is the Internet of Things in Australia (June 2022)

The secret behind strategic tech partnerships that win global goals

The secret behind strategic tech partnerships that win global goals

Poll

What would you like to see more of on BiT?
News
Reviews
Features
How To's
Lollies
Photo Galleries
Videos
Opinion
View poll archive
All rights reserved. This material may not be published, broadcast, rewritten or redistributed in any form without prior authorisation.
Your use of this website constitutes acceptance of nextmedia's Privacy Policy and Terms & Conditions.